科技创新
Innovation

Cantilever practice requirements

2020-06-01 16:31:31 Zhejiang Huayang Construction Co., Ltd. Read

The outside of the pick frame must be enclosed and enclosed by a qualified dense-mesh safety net. The safety net should be hung tightly with no less than 18 # lead wire, and the safety net should be hung on the inside of the stand pole. Outside.

When the distance between the scaffold and the building is greater than 20cm, the standing person should be laid. In addition to the 1.2m high protective railing outside the pick frame and the 180mm high kick bar, when the inner side of the pick frame meets the edge (such as large bay windows, door openings, etc.), corresponding protection should also be provided.

The bottom of the cantilevered external scaffolding (at the cantilever beam) is sealed with hard protection (formwork) and the bottom of the tight hard protection (formwork) should be painted with yellow and black paint.

Qualified safety nets or other measures should be adopted to carry out segmented closed protection on the working layer and bottom layer of the picking frame.

The cantilever construction must be carried out in strict accordance with the approved plan.


The construction of scaffolding is usually the top priority of construction safety. Only when the construction of scaffolding is done well can we be qualified to talk about safe and civilized construction. In actual construction, accidents caused by scaffolding are not uncommon, causing

Countless casualties and property losses. Therefore, the construction safety of the scaffolding should be guaranteed from the details, and the operation should be strictly in accordance with the construction points of the scaffolding. The following scaffolding and internal support

The company's standard practice for supporting and unloading platforms should be kept in mind during the construction of each project department of Huayang Construction.


Copyright © 2019 huangyangjianshe.com All Rights Reserved.